An old fibro house pulled down and rebuilt on the same spot, four bedrooms over two storeys
A$780,000240 m²38 weeks
A$780,000Published by builder
GST not included · land not included · a contract price the builder chose to make public
Type
Knockdown rebuild
Lot area
580 m²
Floor area
240 m²
Per square metre
A$3,250 / m²
Build time
38 weeks
Approval path
DA, council decides
Before and after
Before · The old fibro house before demolitionAfter · The new frame going up
More photos
What happened on this one
Sample data. The old fibro house was past repairing, so it came down and went up again. Four bedrooms over two storeys, with one room downstairs left open as a study or a room for a parent.
Key decisions
The old footings were checked and could not be kept, so the whole house came down.
Sample data · the builder's account
The downstairs room was left without a fixed use; the owner said a parent may live in it later.
Sample data · the builder's account
What the price covers
Included
· Demolition
· Foundation
· Structure
· External walls
· Roof
· Plumbing and electrical
· Kitchen
· Bathroom
· Flooring
· Painting
Not included
· Land
· Earthworks
· Council fees
· Solar
· Fencing
What went into it
FacadeFace brickSample Suppliernamed by the builder
RoofColorbond steel roofingSample Suppliernamed by the builder
WindowsAluminium double glazingSample Suppliernamed by the builder
FlooringEngineered oak flooringSample Suppliernamed by the builder
No prices here. What a supplier charges a builder is not what the same thing would cost you.
Sources: a builder published price is a contract price the builder chose to make public and the platform does not guarantee it. An owner reported price comes from the owner and the platform has not checked it. A declared cost is the estimate an applicant lodged with government and is not a contract price. The three are measured differently, so they cannot be compared directly.