Residential building applications lodged in this suburb over the last 12 months: what was lodged, what it was declared to cost, and how far each one has got. Every number comes from the government planning register.
Applications in 12 months
10
Of those, determined
7
Median DA approval time
8 weeks
Shoalhaven City Council, whole council area
| Type | Applications in 12 months | Median declared cost |
|---|---|---|
| Alterations and additions | 5 | A$62,000 |
| Other | 5 | A$15,000 |
The declared cost is the applicant own estimate, used to work out the lodgement fee. It is not a contract price.
1 September 2026ApprovedApproved · CDC Accepted
declared cost A$51,550, not a contract price
27 July 2026Under assessmentAdditional Information Requested · CDC Accepted
declared cost A$50,000, not a contract price
declared cost A$35,000, not a contract price
28 April 2026Under assessmentAdditional Information Requested · CDC Accepted
declared cost A$15,000, not a contract price
declared cost A$6,249, not a contract price
8 April 2026ApprovedApproved · CDC Accepted
declared cost A$62,000, not a contract price
3 February 2026ApprovedApproved · CDC Accepted
declared cost A$300,000, not a contract price
declared cost A$220,000, not a contract price
declared cost A$8,550, not a contract price
declared cost A$140,550, not a contract price
declared cost A$30,000, not a contract price
Only applications the register itself records as approved appear here. In states whose registers publish only that a decision was made, this section does not appear.
One email a week for West Nowra: what was lodged, what was approved, what got built.
Used for this alert only. Every email carries an unsubscribe link.
Data from the states public planning registers and licence rolls · refreshed 2026-09-14 · Data and licences
Source: the government planning register for this state, with no applicant names. The window runs 2025-09-20 to 2026-09-20. The declared cost is the applicant own estimate, used to work out the lodgement fee. It leaves out GST and land, and it is not the final contract price. The median approval time is worked out across the whole of Shoalhaven City Council, not this one suburb.
Nov 2025 to Sept 2026: 10 applications lodged in West Nowra, one dot each.