Auckland Airport Processing Facility Project Milestone: 10,000 Cubic Metres of Concrete Poured

Industrial · Auckland, Auckland

Auckland Airport Processing Facility Project Milestone: 10,000 Cubic Metres of Concrete Poured

Machine translationThis text was translated by machine. The original is what the person who posted it wrote.

Ask the company about the cost

More photos

Auckland Airport Processing Facility Project Milestone: 10,000 Cubic Metres of Concrete PouredAuckland Airport Processing Facility Project Milestone: 10,000 Cubic Metres of Concrete Poured

The numbers on this project

Type
Industrial

More details to come

What happened on this one

Since September 2024, Livefirm has undertaken the concrete works for the Auckland Airport Domestic Processor project, completing the pouring of 10,000 cubic metres of concrete, 1900 metres of formwork and 19,000 square metres of flooring. The project is scheduled to complete all foundation works by October 2025.

Send this one on

This page is already public. The link goes straight out.

Same suburb, same type

Sources: a builder published price is a contract price the builder chose to make public and the platform does not guarantee it. An owner reported price comes from the owner and the platform has not checked it. A declared cost is the estimate an applicant lodged with government and is not a contract price. The three are measured differently, so they cannot be compared directly. A figure marked "On the builder's website" or "Budget on the builder's website" was read as written from the company's own site and is not a contract price.

Contact this company